Question: Crash the following project: Activity Immediate Predecessor Expected Time Normal Cost Crash Cost per Day Maximum Crash Time A 7 $3,000 $500 3 B 4.33

Crash the following project:

Activity Immediate Predecessor Expected Time Normal Cost Crash Cost per Day Maximum Crash Time
A 7 $3,000 $500 3
B 4.33 $5,000 $1,000 2
C A, B 5 $6,000 0
D C 20 $20,000 $3,000 3
E C 11 $10,000 $1,000 2
F E 7 $7,000 $1,000 1
G C 12 $20,000 $3,000 2
H D, F, G 6 $8,000 $2,000 1
I G, F 9 $5,000 $2,000 1
J H 5 $7,000 $1,000 1
K I, J 29.67 $12,000 $1,000 0

**Note, I would like to see steps for when an activity is crashed, and its effects on the total project so it can be determined how many days to crash is optimal, based on cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!