Question: Given the data and information that follows in this example, compute the slope and maximum reduction time for each activity.Also compute the total direct costs
Given the data and information that follows in this example, compute the slope and maximum reduction time for each activity.Also compute the total direct costs for durations 32, 31, 30, 29, 28, and 27 time-units.
Assume indirect costs of $170,$150, $129, $122, $118, and $110, respectively, for each listed duration. What are the optimum project duration and cost?
The answer has to be in the form of the attached tables. Explain in detail the steps.




\fThe 4th and 5th decisions TIME B TOTAL DIRECT A E COST ACTIVITIES CHANGED C F TIME B D TOTAL DIRECT A COST ACTIVITIES CHANGED C F The total impact Project 27 28 30 31 32 Duration Total Direct Total Indirect $110 $122 $129 $150 $170 Grand TotalThe first decision B TIME 32 D 16 LEGEND 8 ACT A E DUR 7 TOTAL DIRECT C F COST S 12 13 B TIME D A E TOTAL DIRECT COST C F ACTIVITIES CHANGEDThe 2nd and 3rd decision TIME B D Exercise 6-2 TOTAL DIRECT A E COST $ ACTIVITIES CHANGED C F TIME B D A TOTAL DIRECT E COST $ ACTIVITIES CHANGED C F
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
