Question: create a forward and bath path analysis of the information below Task Name Duration Cost Predecessors 1 Hanger Permitting 9 days 2 Application 7 days
create a forward and bath path analysis of the information below
| Task Name | Duration | Cost | Predecessors | |
|---|---|---|---|---|
| 1 | Hanger Permitting | 9 days | ||
| 2 | Application | 7 days | 2,800 | |
| 3 | Process time | 0 days | 0.00 | 2 |
| 4 | Order building materials | 2 days | 560 | 3 |
| 5 | Hangar Permitting Complete | 0 days | 4 | |
| 6 | Hangar Ground Work | 65.3 days | ||
| 7 | Survey property | 3 days | 3,600 | 5 |
| 8 | Set elevation | 7 days | 16,800 | 7 |
| 9 | Prepare site for concrete | 5 days | 12,000 | 8 |
| 10 | Construct tarmac and hangar foundation | 22 days | ||
| 11 | Build concrete forms | 14 days | 39,200 | 9 |
| 12 | Install plumbing passing through concrete (Internal Sewer) | 3 days | 1,080 | 11 |
| 13 | Schedule code inspections | 1 day | 360 | 5, 12 |
| 14 | Order concrete | 1 day | 2,800 | 12 |
| 15 | Pour concrete | 3 days | 8,400 | 12, 14 |
| 16 | Concrete cured | 0 days | 0.00 | 15+7 days |
| 17 | Order specialty equipment | 2 days | ||
| 18 | Compressors and air systems | 1 day | 100,440 | 5 |
| 19 | Crane and lift equipment | 1 day | 250,440 | 5 |
| 20 | Hangar Groundwork Complete | 0 days | 0.00 | 16 |
| 21 | Hangar Assembly | 189.4 days | ||
| 22 | Assemble Frame | 30 days | 84,000 | 16, 19 |
| 23 | Install Crane | 7 days | 3,460 | 22 |
| 24 | Assemble outer structure | 30 days | 84,000 | 23 |
| 25 | Install Hangar Door | 14 days | 39,200 | 23 |
| 26 | Install electrical systems | 30 days | 8,400 | 22 |
| 27 | Install low voltage systems | 30 days | 9,600 | 22 |
| 28 | Install plumbing systems | 91.4 days | ||
| 29 | Air systems | 30 days | 210,800 | 18, 24 |
| 30 | Water systems | 30 days | 260,000 | 18, 24 |
| 31 | External Sewer systems | 30 days | 310,800 | 24 |
| 32 | Connect to outside sources | 1.4 days | 82,763 | 24, 25, 26, 27, 28, 29, 30, 31 |
| 33 | Finish inside areas | 30 days | 342,890 | 32 |
| 34 | Hangar Assembly Complete | 0 days | 0.00 | 33 |
| 35 | Open House | 1 day | 12,500 | 34 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock