Question: Create a forward backwards pass for the following Task Outline # Name Duration Predecessors Start Finish a 1 Design and plan for custom home 8

Create a forward backwards pass for the following
Task Outline # Name Duration Predecessors Start Finish
a 1 Design and plan for custom home 805/31/202406/08/2024
b 1.1 Produce high level schematic design 305/31/202406/03/2024
c 1.2 Produce architectural plans 5 b 06/03/202406/08/2024
d 1.2.1 Produce site plan 5 b 06/03/202406/08/2024
e 1.2.2 Produce floor plan 5 b 06/03/202406/08/2024
f 1.3 Produce detailed design 3 a 05/31/202406/03/2024
g 1.3.1 Produce structural design 3 a 06/05/202406/08/2024
h 1.3.2 Produce mechanical design 3 a 06/05/202406/08/2024
i 1.3.3 Produce plumbing design 3 a 06/05/202406/08/2024
j 1.3.4 Produce electrical design 3 a 06/05/202406/08/2024
k 1.3.5 Produce civil design 3 a 06/05/202406/08/2024
l 1.3.6 Produce landscape design 3 a 06/05/202406/08/2024
m 1.3.7 Produce water features design 3 a 06/05/202406/08/2024
n 2 Execute preconstruction 2206/08/202406/30/2024
o 2.1 Conduct site survey 5 a 06/08/202406/13/2024
p 2.2 Gather necessary permitting 10 a 06/08/202406/18/2024
q 2.3 Conduct site clearing 10 a,o,p 06/18/202406/28/2024
r 2.4 Conduct site prep 5 a,o,p 06/18/202406/23/2024
s 2.5 Make procurements 20 a 05/31/202406/20/2024
t 2.6 Execute subcontracting 10 a 05/31/202406/10/2024
u 2.7 Perform materials staging 2 a,q,o,p,r,s 06/28/202406/30/2024
v 3 Execute construction 5006/30/202408/19/2024
w 3.1 Run lines for utilities and internet 2 n 06/30/202407/02/2024
x 3.2 Lay foundation 10 n 06/30/202407/10/2024
y 3.3 Build structure 50 n,x 07/10/202408/29/2024
z 3.4 Buildout and finish exterior 20 n,x 07/10/202407/30/2024
aa 3.5 Buildout and finish interior 20 n,x 07/05/202407/25/2024
ab 3.6 Terminate utility and internet connections 2 w 07/02/202407/04/2024
ac 3.7 Perform landscaping 10 z 07/30/202408/09/2024
ad 3.8 Get inspections and reports 10 ac 08/09/202408/19/2024
ae 4 Execute post construction 1308/09/202408/22/2024
af 4.1 Perform site cleanup 5 ac 08/09/202408/14/2024
ag 4.2 Perform walkthrough inspection 1 ad 08/19/202408/20/2024
ah 4.3 Closeout inspection punch list items 2 ad 08/19/202408/21/2024
ai 4.4 Complete project sign off 1 ah 08/21/202408/22/2024
aj 5 Execute Project Management 2706/08/202407/05/2024
ak 5.1 Select subcontractors 5 n 06/30/202407/05/2024
al 5.2 Manage the project 0 a 06/08/202406/08/2024
Potential top level deliverables
Custom home
High-level schematic design
Architectural plans
Site plan
Floor plan
Overall detailed design to include the following elements:
Structural
Mechanical
Plumbing
Electrical
Civil
Landscape
Water Features (swimming pool and waterfall)
Inspection reports
 Create a forward backwards pass for the following Task Outline #

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!