Question: Create a Gannt chart with the following information provided below. After you finish entering the tasks, use the Indent button () on the formatting toolbar

Create a Gannt chart with the following information provided below.

After you finish entering the tasks, use the Indent button () on the formatting toolbar to adjust the relationship between tasks until it properly show the above relationships.

Task 2. Specify the duration for each task

Add information to the duration column

  1. Finish the Project Outline (1 day, start Oct 16, 2020)
  2. Research
    1. Dividing projects into pieces for team member (3 days)
    2. Team member 1 Data Collection (5 days)
    3. Team member 1 Data Analysis (10 days)
    4. Team member 2 Data Collection (7 days)
    5. Team member 2 Data Analysis (14 days)
    6. Team member 3 Data Collection (7 days)
    7. Team member 3 Data Analysis (10 days)
    8. Team member 4 Data Collection (12 days)
    9. Team member 4 Data Analysis (10 days)
    10. Milestone 1: Finish Data Collection (0 day)
  3. Paper Write-up and Presentation
    1. First Draft
      1. Write the draft (5 days)
      1. Edit the Paper (3 days)
      2. Milestone 2: Finish first draft (0 day)
    1. Presentation
      1. Prepare for Presentation (7 days)
      1. Milestone 3: Final Presentation (0 day)
    1. Paper Revision (5 days)
    2. Milestone 4: Final Paper Submission (0 day)

Task 3. Sequencing Tasks

Specify the following interdependencies:

  1. Research has to start after you Finish the Project Outline.
    • put the task id of the Finish the Project Outline (1) in the field of predecessors for task Research.
  2. For all four team members, Data collection starts after Dividing projects into pieces and Data 1analysis part starts after the Data Collection.
  3. Milestone 1 starts when all the 4 team members finish data analysis.
  4. Paper Write-up and Presentation starts after the Milestone 1.
  5. Under first draft, the sequence should be: Writeup the paper edit the paper Milestone 2.
  6. For Presentation, the sequence should be Prepare for Presentation Milestone 3.
  7. Paper Revision starts after Milestone 2 and 3, followed by Milestone 4.

Task 4. Adjusting and Tracking Tasks

  1. Set the final presentation date on Dec 4, 2020.
  2. Set the task completion rate of Task 1 Finish the Project Outline to 100%
  3. Set Task 3 Diving projects into pieces for team member to 50% complete.

Congratulations! Now youve have the Gantt Chart.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!