Question: Create a network diagram for the forward and backward pass. Include earliest/latest start & finish, slack. What is the critical path? What is the expected

Create a network diagram for the forward and

Create a network diagram for the forward and

Create a network diagram for the forward and backward pass. Include earliest/latest start & finish, slack.

What is the critical path?

What is the expected time of completion for the project?

+ Time (days) Immediate Processers 14 Activity A. Grading B. Excavation C. Structural D. Plumping E. Electrical F. Equipment Installed G. Gunite Pool H. Addition Drainage I. Concrete J. Coping Pool K. Irrigation L. Plant M. Lawn N. Lighting 19 | C, D, E, F |