Question: Create an activity on arrow diagram based on the following information: Task A, duration 6, dependent on none Task B, duration 5, dependent on none
Create an activity on arrow diagram based on the following information:
Task A, duration 6, dependent on none
Task B, duration 5, dependent on none
Task C, duration 3, dependent on none
Task D, duration 12, dependent on Task B and Task C
Task E, duration 2, dependent on Task A
Task F, duration 5, dependent on Task B
Task G, duration 1, dependent on Task B