Question: Create an activity on arrow diagram based on the following information: Task A, duration 6, dependent on none Task B, duration 5, dependent on none

Create an activity on arrow diagram based on the following information:

Task A, duration 6, dependent on none

Task B, duration 5, dependent on none

Task C, duration 3, dependent on none

Task D, duration 12, dependent on Task B and Task C

Task E, duration 2, dependent on Task A

Task F, duration 5, dependent on Task B

Task G, duration 1, dependent on Task B