Question: Create gant chart for the wbs and duration is for febuary 2023 to july 2023 Project Initiation 1.1 Define project objectives and requirements, 1.2 Conduct
Create gant chart for the wbs and duration is for febuary 2023 to july 2023
|
1.1 Define project objectives and requirements, |
1.2 Conduct a feasibility study, |
1.3 Secure necessary permits and approvals, |
|
2.1 Hire an architect or designer, |
2.2 Develop architectural and structural drawings, |
2.3 Prepare detailed plans for electrical, plumbing, and HVAC systems, |
2.4 Obtain necessary design approvals, |
|
3.1 Clear the construction site, |
3.2 Excavate and grade the land, |
3.3 Install temporary fencing and signage, |
|
4.1 Excavate and lay foundation footings, |
4.2 Pour and cure concrete foundation, |
4.3 Construct walls and load-bearing structures, |
4.4 Install roof trusses or beams, |
MEP
|
5.1 Rough-in plumbing lines (water supply, drainage, etc.), |
5.2 Install plumbing fixtures (sinks, toilets, showers, etc.), |
5.3 Rough-in electrical wiring and outlets, |
5.4 Install electrical fixtures (lights, switches, outlets, etc.), |
|
6.1 Install ventilation, and air conditioning (HVAC) systems, STOP HERE |
6.2 Insulate walls, floors, and ceilings, |
6.3 Install vapor barriers and insulation materials, |
|
7.1 complete wall finishes, |
7.2 Apply paint or wallpaper, |
7.3 Install flooring materials (tiles, hardwood, carpet, etc.) |
7.4 Install doors, windows, and trim, |
7.5 Install built-in cabinets and shelving, |
|
8.1 Install kitchen cabinets and countertops, |
8.2 Install bathroom fixtures (sink, toilet, shower, etc.) |
8.3 Install light fixtures and switches 8.4 Install appliances (stove, refrigerator, dishwasher, etc.) |
|
9.1 Conduct final inspections |
9.2 Clean the construction site, |
9.4 Address any punch list items, |
9.5 Obtain a certificate of occupancy, |
|
10.1 Document as-built drawings and specifications, |
10.2 Complete final paperwork and financials |
10.3 Hand over keys to the owner |
10.4 Conduct post-construction evaluation and lessons learned. |
Step by Step Solution
3.40 Rating (150 Votes )
There are 3 Steps involved in it
Project Initiation Define project objectives and requirements Duration 2 weeks Conduct a feasibility study Duration 3 weeks Dependency 1 Secure necess... View full answer
Get step-by-step solutions from verified subject matter experts
