Question: Using the information from a project below: Activity Predecessor Duration (Days) A - 10 B - 9 C - 13 D A;B 15 E B;C
Using the information from a project below:
Activity Predecessor Duration (Days)
A - 10
B - 9
C - 13
D A;B 15
E B;C 17
F D;E 18
G F 10
1 Construct the network diagram (AON) and identify the Critical Path.
2 Calculate the Early Start; Late Start; Early Finish & Late Finish for all activities.
3 Compute the slack time for each activity.