Question: Critical Path and Gantt Chart Assignment **This assignment is actually graded as two assignments for the week. Stadium Builders RS are preparing a bid to

Critical Path and Gantt Chart Assignment **This assignment is actually graded as two assignments for the week. Stadium Builders RS are preparing a bid to build a new 50,000 seat baseball stadium in Delaware. The construction must start on June 1, 2013 and be completed in time for the 2016 season. A penalty clause of $90,000 per day of delay beyond April 20, 2016 is written into the contract. Willie Robertson, the president of the company could net as much as $1.9MM on the project. He also said if they are successful, the prospects for future projects are very good since there is a projected interest in building new ball parks with modern luxury boxes. Given the information provided below for the stadium project. answer the following questions: Assignment A (25 points) 1. 2. 3. 4. Will the project be completed by the April 20th deadline? How long will it take? What is the critical path for the project? Based on the schedule, would you recommend that the new owner pursue this construction contract? Why or Why not? Assignment B (25 points) 5. Include a one page Gantt chart for the stadium schedule. ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Activity Baseball Stadium Get permits Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Duration Predecessor(s) 10 days 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days ----3 4 3 6 4,7 4,7 4,7 8, 10 8, 10 8, 10 8, 10 11 16 17 Light installation Build roof supports 30 days 90 days 15 7 18 19 20 21 Construct roof Install roof tracks Install roof Inspection 180 days 90 days 90 days 20 days 17 17 18, 19 9,12,14,16,20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!