Question: Critical Path Method Activity Precedent Duration (days) A NONE 15 B A 10 C A 8 D A 3 E B 6 F B,C,D 3
Critical Path Method
Activity
Precedent
Duration (days)
A
NONE
15
B
A
10
C
A
8
D
A
3
E
B
6
F
B,C,D
3
G
E,F
4
Based on the information supplied above:
1.Draw
a Critical Path Precedence Network, perform a Forward Pass, a Backward Pass, find Slack for each activity and identify the Critical Path.