Question: Critical Path Method Activity Precedent Duration (days) A NONE 15 B A 10 C A 8 D A 3 E B 6 F B,C,D 3
Critical Path Method
| Activity | Precedent | Duration (days) |
| A | NONE | 15 |
| B | A | 10 |
| C | A | 8 |
| D | A | 3 |
| E | B | 6 |
| F | B,C,D | 3 |
| G | E,F | 4 |
Based on the information supplied above:
1. Draw (on an 8.5" X 11" piece of paper) a Critical Path Precedence Network, perform a Forward Pass, a Backward Pass, find Slack for each activity and identify the Critical Path.
2. Transfer/ Type the information into the answer table below:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
