Question: answer by hand and show all work Activity Predecessor Duration (days) A None 10 B A 8 4 D B 3 E D F 2

answer by hand and show all work Activity
answer by hand and show all work Activity
answer by hand and show all work
Activity Predecessor Duration (days) A None 10 B A 8 4 D B 3 E D F 2 G E, F 12 H G 4 1) Given the information above, what is the project duration? (3 pts) 2) Which activities are on the critical path (write all that apply) (5 pts) 3) Activity His a packaging process. A new activity, Activity S, describes the shipping process. Duration for Activity Sis 3 days. Shipping can begin as early as one day after the packaging process begins. There is no need to wait for all products to be packaged before shipping can begin. What type of lag is being described here? (3 pts) Considering this new activity and its relationships, what is the new project duration? (3 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!