Question: 24. Activity Predecessor Duration (weeks) a none 4 b none 5 c a, b 8 d c, e 6 e b 2 f e 9

24.

Activity Predecessor Duration (weeks)
a none 4
b none 5
c a, b 8
d c, e 6
e b 2
f e 9
g d 7
h f,g 4

Your firm is working on a Sales and Operations improvement project. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. What is the length of the project?

32

30

34

29

What is the critical path for this project?

B-E-F-H

There is more than one critical path

B-E-D-G-H

A-C-D-G-H

B-C-D-G-H

25.

Activity Predecessor Duration (weeks)
a none 12
b none 5
c a, b 7
d c, e 2
e b 8
f e 9
g d 5
h f,g 8

Your firm is implementing a balanced scorecard. As the project manager, you need to make sure the project is completed on time and on-budget. The table below lists the steps that need to be complete. The data analysis team members are going to be late deliverig some key data points that are needed to complete the project (activity B). How many weeks can this activity be delayed without delaying the completion of the project?

3

0

4

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!