Question: Critical Path Method (CPM) Activity a b d Preceding Preceding Succeeding Duration activities events events None 1 2 3 None 1 3 6 None 1

Critical Path Method (CPM) Activity a b d

Critical Path Method (CPM) Activity a b d Preceding Preceding Succeeding Duration activities events events None 1 2 3 None 1 3 6 None 1 4 8 a 2 5 7 b 3 5 5 4 5 10 4 6 4 d, e, f 5 7 5 g 6 7 6 e f C bolc h i You are required- 1. Draw the network 2. Find the critical path by complete enumeration 3. Find for all events the earliest date and latest date. 4. Find the slack for all events and activities 5. Find the critical path by using TE's and TL's