Question: ctivity Immediate Predecessor Duration (days) Start A Start 3 B F 4 C H 7 D Start 4 E D 9 F D & A
ctivity Immediate Predecessor Duration (days)
Start
A Start 3
B F 4
C H 7
D Start 4
E D 9
F D & A 8
G E & F 4
H G 2
End B, C
Given the above activities, predecessors, and duration, draw a network diagram on the paper and answer the questions (you don't have to submit the diagram).
What is the critical path? (Write the letters in the proper order)
| a. | AEFG | |
| b. | ABCDE | |
| c. | DEGHC | |
| d. | ACGH |