Question: ctivity Immediate Predecessor Duration (days) Start A Start 3 B F 4 C H 7 D Start 4 E D 9 F D & A

ctivity Immediate Predecessor Duration (days)

Start

A Start 3

B F 4

C H 7

D Start 4

E D 9

F D & A 8

G E & F 4

H G 2

End B, C

Given the above activities, predecessors, and duration, draw a network diagram on the paper and answer the questions (you don't have to submit the diagram).

What is the critical path? (Write the letters in the proper order)

a.

AEFG

b.

ABCDE

c.

DEGHC

d.

ACGH