Question: d) In Planning for a project schedule, a project manager has generated the following information Activity Predecessor Activity Duration (Days) A 7 B 10 A

d) In Planning for a project schedule, a project manager has generated the following information Activity Predecessor Activity Duration (Days) A 7 B 10 A 4 D A 30 E A 7 F B,C 12 G B,C 15 H E,F 11 1 E,F 25 J E,F 6 K DH 21 L GJ 25 i. ii. Which techniques of analysis would you use to analyze this information and why (1 Mark) Represent the above information using a network diagram ( 4 Marks) Determine the project completion time and show its critical path in the diagram iii. iv. (2 Marks) Compute the probability of completing this project within 40 Days (2 Marks)