Question: D Question 32 3 pts Given the following activity network A2 AI A3 weeks Activity A1 takes 5 weeks A2 takes 6 weeks, and A3

D Question 32 3 pts Given the following activity
D Question 32 3 pts Given the following activity network A2 AI A3 weeks Activity A1 takes 5 weeks A2 takes 6 weeks, and A3 takes 3 weeks. What is the tatest start time of A3? (round to the nearest Integer) I Next Previous Am Submit