Question: Question 2 4 3 pts Given the following activity network: Activity A 1 takes 3 weeks, A 2 takes 5 weeks, A 3 takes 7

Question 24
3 pts
Given the following activity network:
Activity A1 takes 3 weeks, A2 takes 5 weeks, A3 takes 7 weeks, A4 takes 3 weeks, A5 takes 4 weeks. What is the earliest project completion time? weeks (round to the nearest integer
 Question 24 3 pts Given the following activity network: Activity A1