Question: You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What

You monitored figures on cost and planned/earned

You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?

A - The project is ahead of schedule and under budget.

B. The project is ahead of schedule and over budget. C. The project is behind schedule and over budget.

D. The project is behind schedule and under budget.

Planned Value Project Week Actual Cost Earned Value 1 SAR 65,000 SAR 61,000 SAR 67,000 2 2 SAR 85,000 SAR 79,000 SAR 89,000 3 3 SAR 100,000 SAR 110,000 SAR 102,000 4 SAR 125,000 SAR 124,000 SAR 121,000 5 SAR 135,000 SAR 133,000 SAR 139,000 6 SAR 125,000 SAR 120,000 SAR 131,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!