Question: You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What

You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. What is the status of this project at this date?
A - The project is ahead of schedule and under budget.
B. The project is ahead of schedule and over budget. C. The project is behind schedule and over budget.
D. The project is behind schedule and under budget.
Planned Value Project Week Actual Cost Earned Value 1 SAR 65,000 SAR 61,000 SAR 67,000 2 2 SAR 85,000 SAR 79,000 SAR 89,000 3 3 SAR 100,000 SAR 110,000 SAR 102,000 4 SAR 125,000 SAR 124,000 SAR 121,000 5 SAR 135,000 SAR 133,000 SAR 139,000 6 SAR 125,000 SAR 120,000 SAR 131,000Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock