Question: 21 (4 points) You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the
21 (4 points) You monitored figures on cost and planned/earned value for each individual project week until the data date at the end of the sixth week. Project Actual Earned Planned week costs value value $65,000 $61,000 $67,000 $85.000 $79,000 $89,000 $100,000 $102,000 $110,000 HNmy ID $125.000 $124,000 $121,000 $135.000 $133,000 $139,000 $125,000 $120,000 $131,000 What is the status of this project at this date? The project is behind schedule and over budget. The project is ahead of schedule and over budget. The project is behind schedule and under budget. The project is ahead of schedule and under budget