Question: Data for AON analysis problems: A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A --

Data for AON analysis problems:

A network consists of the activities in the following list. Times are given in weeks.

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A, B

3

E

C

4

F

D

9

Note: draw the network diagram based on activity on node and answer test1 questions with ID AON

Data for decision tree problems:

JDI, Inc. is trying to decide whether to make or buy a part (#J-45FPT). Purchasing the part would cost $1.30 each. If they design and produce it themselves, it will result in a per unit cost of $0.82. However, the design investment would be $40,000. Further, they realize that for this type of part, there is a 25% chance that the part will need to be redesigned at an additional cost of $50,000. Regardless of whether they make or buy the part, JDI will need 80,000 of these parts. Using decision trees analysis and EMV, what should JDI do?

Note: draw the decision tree and answer test1 questions with ID Decision tree

ID Decision tree What is leaf value of the path with failure?

$115,200

$121,500

$155,600

$175,000

6 points

QUESTION 16

ID decision tree What is the expected value of the decision node?

$115,200

$121,800

$145,600

$118,100

6 points

QUESTION 17

IDF1 A forecaster trusts both most recent data points and the middle data points three times the oldest data point in a 3-point MA method (as discussed in the class). The weights that are used for the method are:

0.143, 0.345, 0.345

0.200, 0.400, 0.400

0.143, 0.428, 0.428

0.255, 0.255, 0.555

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!