Question: Based on this data: Data for AON analysis problems: A network consists of the activities in the following list. Times are given in weeks. Activity
Based on this data:
Data for AON analysis problems:
A network consists of the activities in the following list. Times are given in weeks.
| Activity | Preceding | Time |
| A | -- | 8 |
| B | -- | 3 |
| C | A | 7 |
| D | A, B | 3 |
| E | C | 4 |
| F | D | 9 |
Note: draw the network diagram based on activity on node and answer test1 questions with ID AON
Respond the following:
1. ID AON What is the slack of activity C?
2. ID AON What is the slack of activity B?
3. ID AON What is project completion time?
D AON What is the LF of activity D?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts