Question: Based on this data: Data for AON analysis problems: A network consists of the activities in the following list. Times are given in weeks. Activity

Based on this data:

Data for AON analysis problems:

A network consists of the activities in the following list. Times are given in weeks.

Activity

Preceding

Time

A

--

8

B

--

3

C

A

7

D

A, B

3

E

C

4

F

D

9

Note: draw the network diagram based on activity on node and answer test1 questions with ID AON

Respond the following:

1. ID AON What is the slack of activity C?

2. ID AON What is the slack of activity B?

3. ID AON What is project completion time?

D AON What is the LF of activity D?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!