Question: Description Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9

Description

Activity

a

m

b

Activity Predecessor

A

3

5

7

--

B

4

8

10

A

C

2

3

5

A

D

6

9

12

B, C

E

5

9

15

D

Using Table ZZ, the variance of the projects total completion time is

A.

5.472 weeks.

B.

5.222 weeks.

C.

4.872 weeks.

D.

3.752 weeks.