Question: Description Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9
| Description |
|
|---|
Using Table ZZ, the variance of the projects total completion time is
| A. | 5.472 weeks. | |
| B. | 5.222 weeks. | |
| C. | 4.872 weeks. | |
| D. | 3.752 weeks. |