Question: Description Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9
| Description |
|
|---|
Using Table ZZ, how much slack is associated with activity C?
| A. | 0 weeks.
| |
| B. | 4.50 weeks. | |
| C. | 12.67 weeks. | |
| D. | 31.00 weeks. |