Question: Description Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9
| Description |
|
|---|
Using Table ZZ, the probability that the project could be completed in 34 weeks or less is approximately
| A. | 86 percent. | |
| B. | 89 percent. | |
| C. | 91 percent. | |
| D. | 96 percent. |