Question: Details Use the attached Activity-on-Arrow (AOA) or Activity-on-Node(AON) project networks to do the following 1. Calculate the Early Start, Early Finish, Late Start, and Late


Details Use the attached Activity-on-Arrow (AOA) or Activity-on-Node(AON) project networks to do the following 1. Calculate the Early Start, Early Finish, Late Start, and Late Finish times for each activity. 2. Identify the critical path for the project and the completion time (assuming all times are stated in weeks) 3. Calculate the activity slack for non-critical activities 4. Identify how much of the activity slack is "shared" with other non-critical activities. You DO NOT have to do both the AOA and AON diagrams Choose whichever orientation you prefer to use. Supporting Materials simple Project Pecedence Diagnam 2opts \& Simple Project Precedence Diagram Simple Project Precedence Diagram