Question: Determine each tasks: Early start and early finish dates Late start and finish dates Calculate the float for each task Identify the critical path and
- Determine each tasks:
- Early start and early finish dates
- Late start and finish dates
- Calculate the float for each task
- Identify the critical path and the total days for the path
- If activity E changes from 5 days to 10 days, what is the impact on the critical path and total duration of the project? Fill out the Table and answer the questions