Question: Determine the critical path. A-C-E-G A-B-D-G A-C-F-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time weeks For the

Determine the critical path.
-
A-C-E-G
-
A-B-D-G
-
A-C-F-G
-
A-B-E-G
a-2. Determine the early completion time in weeks for the project.
Early completion time weeks
For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.
| ACTIVITY | NORMAL TIME | NORMAL COST | CRASH TIME | CRASH COST | ||||
| A | 6 | $ | 7,500 | 2 | $ | 12,200 | ||
| B | 14 | 12,700 | 8 | 18,700 | ||||
| C | 7 | 5,300 | 5 | 8,500 | ||||
| D | 5 | 4,600 | 4 | 6,400 | ||||
| E | 6 | 3,700 | 5 | 4,600 | ||||
| F | 5 | 6,500 | 3 | 8,900 | ||||
| G | 2 | 7,300 | 1 | 7,900 | ||||
b-1. Which activities in order of reduction would be shortened?
-
B-G-D
-
G-E-A
-
D-B-C
-
G-B-B
b-2. Find the resulting cost to crash.
Resulting cost $
D15) B(14) A[6) E16) G2) (C17 F(5Step by Step Solution
There are 3 Steps involved in it