Question: Determine the critical path. A-C-E-G A-B-D-G A-C-F-G A-B-E-G a-2. Determine the early completion time in weeks for the project. Early completion time weeks For the

Determine the critical path. A-C-E-G A-B-D-G

Determine the critical path.

  • A-C-E-G

  • A-B-D-G

  • A-C-F-G

  • A-B-E-G

a-2. Determine the early completion time in weeks for the project.

Early completion time weeks

For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened.

ACTIVITY NORMAL TIME NORMAL COST CRASH TIME CRASH COST
A 6 $ 7,500 2 $ 12,200
B 14 12,700 8 18,700
C 7 5,300 5 8,500
D 5 4,600 4 6,400
E 6 3,700 5 4,600
F 5 6,500 3 8,900
G 2 7,300 1 7,900

b-1. Which activities in order of reduction would be shortened?

  • B-G-D

  • G-E-A

  • D-B-C

  • G-B-B

b-2. Find the resulting cost to crash.

Resulting cost $

D15) B(14) A[6) E16) G2) (C17 F(5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!