Question: Determine the critical path and the project completion time. Normal Crash Normal Crash Crash Cost Determine the crash cost per week for all activities. Complete

Determine the critical path and the project completion time. Normal Crash Normal Crash Crash Cost
Determine the crash cost per week for all activities. Complete the Chart at the Right Activity Slack Time Time Cost Cost Per Week
A 074 $400 $750
B 1129 $1,000 $2,200
C 076 $800 $1,100
D 065 $600 $1,000
E 086 $1,200 $2,200
F 932 $800 $1,000
G 932 $500 $650
H 043 $400 $600
I 065 $900 $1,300