Question: develop a gantt chart for following activities. Identify all path through network what is critical path? activity expected duration predecessor A 3 DAYS -- B

develop a gantt chart for following activities. Identify all path through network what is critical path? activity expected duration predecessor A 3 DAYS -- B 3DAYS A C 5 days A D 3 DAYS B,C E 4DAYS B F 6DAYS D G 4 DAYS C,E,F