Question: 1. Considering the following project, determine the Critical Path? Activity Expected Duration Predecessor A 5 - B 3 A C 1 A, B D 5

1. Considering the following project, determine the Critical Path?

Activity

Expected Duration

Predecessor

A 5 -
B 3 A
C 1 A, B
D 5 C
E 10 B
F 2 E
G 3 D
H 4 F, G
I 5 H

Notes:

- Durations are in days.

2. Calculate the total project duration (project expected duration + buffer) to get a 95% confidence of delivering the project on time?

Notes:

- All activities respond to a beta distribution. The expected duration is the mean value of the beta distribution.

- Consider that all activities have a standard deviation equal to 30% of their expected duration.

- Round up the project duration to an integer number.

3. The project sponsor asked you to reduce the project duration by 3 days. You decide to crash one or more activities. Which activity would you crash first and why? Explain your assumptions if any.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!