Question: In the Forward and Backward passes that we do to determine the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF)
In the Forward and Backward passes that we do to determine the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF) of the activities, wvhich one of the following statements is FALSE To start the backward pass, we set LF of the ending node equal to its ES The LS of an activity is equal to the LE of this activity minus its duration to start the forward pass, we set ES of the starting node equal to zero The EF of an activity is equal to the ES of this aetivity plus its duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
