Question: Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the
Develop a resource schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Note: activities 2, 3, 5, and 6 use two of the resource skills. Three of the resource skills are available. After scheduling, find the following: a-slack for activity 1,b- slack for activity 3, c-slack for activity 4 d-which activities are critical now, e- list the sequence of the activates.Single line text.