Question: develop an initial project network diagram showing the schedule of eqch activity. also how many workers you will assign to tasks each week. the most

develop an initial project network diagram showing the schedule of eqch activity. also how many workers you will assign to tasks each week. the most workers on any given task is two per week develop an initial project network diagram
Table 1 Activity Description Duration (weeks) 3 5 Immediate predecessors A B D E F G H Negotiate contracts with music groups Have a construction firm build the stage Negotiate contract with roadies Hire security personnel Arrange ticket distribution Arrange advertising and souvestir program printing Arrange music group transportation Arrange sound equipment Process travel visas for international groups Arrange parking Distribute media passes and arrange for MTV recording Arrange concession sales and restroom facilities 3 1 4 1 3 I A D E CD FH E, B, H G F 5 4 J K L 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!