Question: Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network and identify
Develop the AON networks based on the following project schedule how long does it takes to complete this project. Draw the AON network and identify the critical path.
|
| |||||
| WBS | ID | Activity | Duration | Cost | Predecessors |
| 1 | 1 | Pool Project |
|
|
|
| 1.1 | 2 | Excavation | 5d | $6,000 |
|
| 1.2 | 3 | Reinforcing structure | 3d | $5,900 | 2 |
| 1.3 | 4 | Install piping | 4d | $3,800 | 3 |
| 1.4 | 5 | Install electrical | 3d | $3,900 | 3 |
| 1.5 | 6 | Blow pool concrete shell | 5d | $13,500 | 5,4 |
| 1.6 | 7 | Install decking | 5d | $6,000 | 6FS+5d |
| 1.7 | 8 | Install pumps and blower | 4d | $4,200 | 7 |
| 1.8 | 9 | Install filtration system | 2d | $3,600 | 7 |
| 1.9 | 10 | Install landscaping | 5d | $6,000 | 9, 8 |
| 1.1 | 11 | Checkout system | 1d | $600 | 10 |
| 1.11 | 12 | Final approval | 0d | $0 | 11 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts