Question: Disaster strikes and activity F takes 2 0 days instead of the anticipated 5 days. Using the table, how much longer will the project last
Disaster strikes and activity F takes days instead of the anticipated days. Using the table, how much longer will the project last than initially estimated?
Activity Predecessor Time days
A
B
C
D AB
E C
F A
G DE
H G