Question: Disaster strikes and activity F takes 2 0 days instead of the anticipated 5 days. Using the table, how much longer will the project last

Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using the table, how much longer will the project last than initially estimated?
Activity Predecessor Time (days)
A --8
B --6
C --3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4