Question: Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G D,E 3
Activity Predecessor Time (days) A -- 8 B -- 6 C -- 3 D A,B 10 E C 8 F A 5 G D,E 3 H G 4 Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated?
Select one: A. 0 days B. 15 days C. 7 days D. 3 days