Question: Do a critical path analysis for this project with including forward pass, backward pass, and critical path information. Thank you Activity Duration (days) Succeeding Activities
Do a critical path analysis for this project with including forward pass, backward pass, and critical path information.
Thank you
| Activity | Duration (days) | Succeeding Activities |
| A | 2 | B, D |
| B | 3 | C |
| C | 3 | F |
| D | 10 | E, F |
| E | 4 | G |
| F | 6 | G |
| G | 3 | none |