Question: DO NOT COPY AND PASTE THE ANSWER FOUND ON CHEGG PLEASE IT IS WRONG - REPOSTING MY QUESTION. THERE ARE 10 WORK DAYS NOT 13

DO NOT COPY AND PASTE THE ANSWER FOUND ON CHEGG PLEASE IT IS WRONG - REPOSTING MY QUESTION. THERE ARE 10 WORK DAYS NOT 13 WORK DAYS

Your team has 4 developers with mostly similar skills. There are 9 tasks that need to be done in the next two weeks, and your job is to assign them so everything gets done in the proper order. No overtime or double-booking is allowed.

Task A: 4 person-days, no dependencies, single developer only Task B: 7 person-days, no dependencies, must be done by developer 4 Task C: 6 person-days, must start after Task A completes, single developer only Task D: 6 person-days, must start after Task B completes, 1 or 2 developers working together Task E: 2 person-days, no dependencies, single developer only Task F: 5 person-days, no dependencies, single developer only Task G: 4 person-days, no dependencies, single developer only Task H: 3 person-days, must start after Task E complete, single developer only Task I: 3 person-days, cannot start before Task C (but can be done at the same time), single developer only

What to turn in: upload an Excel file or a screenshot of your spreadsheet (other spreadsheet apps are fine) chart showing the 4 developers as rows, the 10 workdays as columns, and the task each should be doing on each day.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!