Question: Draw a Critical Path Method ( CPM ) diagram for the project. b ) Identify the critical path c ) Determine the project completion time.

Draw a Critical Path Method (CPM) diagram for the project.
b) Identify the critical path
c) Determine the project completion time.
Upload your solution in the form of a Word document.
Activity Immediate Predecessor(s) Time (Days)
A --9
B A 7
C A 3
D B 6
E B 9
F C 4
G E, F 6
H D 5
I G, H 3