Question: Draw a critical path method network for the following information, and draw a table consisting of earliest start, earliest finish, latest start, latest finish, and
Draw a critical path method network for the following information, and draw a table consisting of earliest start, earliest finish, latest start, latest finish, and slack for each activity.

Please and thank you~
\begin{tabular}{|l|l|r|} \hline Activity & Immediate predecessor(s) & Time (Weeks) \\ \hline A & None & 3 \\ \hline B & None & 4 \\ \hline C & A & 6 \\ \hline D & B & 9 \\ \hline E & B & 6 \\ \hline F & C,D & 6 \\ \hline G & D, E & 8 \\ \hline H & G,F & 9 \\ \hline \end{tabular} \begin{tabular}{|l|l|r|} \hline Activity & Immediate predecessor(s) & Time (Weeks) \\ \hline A & None & 3 \\ \hline B & None & 4 \\ \hline C & A & 6 \\ \hline D & B & 9 \\ \hline E & B & 6 \\ \hline F & C,D & 6 \\ \hline G & D, E & 8 \\ \hline H & G,F & 9 \\ \hline \end{tabular}