Question: Draw a Gantt chart for the following project using ProjectLibre. Assume that durations are in days and that the project starts on March 1 of
Draw a Gantt chart for the following project using ProjectLibre.
Assume that durations are in days and that the project starts on March 1 of the current year. Also assume that your employees do not work on national holidays or on the weekend.
| Activity | Duration | Predecessors |
| A | 5 |
|
| B | 8 | A |
| C | 4 | A |
| D | 3 | B |
| E | 5 | C |
| F | 2 | D and E |
In the program, generate a PDF with the project tasks, durations, predecessors, and Gantt chart. Submit 2 files to this assignment for grading: 1) ProjectLibre native save file for the project, and 2) PDF Generated by ProjectLibre of the Gantt chart. ZIP files and incomplete submissions will not be accepted or graded.