Question: . Draw a network diagram (using the quadrants) . Determine the early start, early finish and late start, late finish for each activity. . Identify


. Draw a network diagram (using the quadrants) . Determine the early start, early finish and late start, late finish for each activity. . Identify the Critical Path . Calculate the slack for each . Indicate how long it will take to complete the project.Project 2 Immediate Activity Predecessor(s) Time (weeks) - - 3 -- 4 - - 2 A 4 A. B 5 A, B. C 2 FIL -IOnMOOOF D. E E 6 E, F 2 G. H, I 4 H. I 3 6
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
