Question: show full working Draw a network diagram (using the quadrants) Determine the early start, early finish and late start, late finish for each activity. Identify

show full working
show full working Draw a network diagram (using
Draw a network diagram (using the quadrants) Determine the early start, early finish and late start, late finish for each activity. Identify the Critical Path Calculate the slack for each Indicate how long it will take to complete the project. Project 1 Immediate Time Activity Predecessor(s) (weeks) A 7 B 9 A 8 D AB 8 E B 9 10 F G D, E 5 H E 10 1 F G 5