Question: Draw a project network diagram for a resource - constrained project from the following information and identify the critical path. ID Predecessor Duration Resources A
Draw a project network diagram for a resourceconstrained project from the following information and identify the critical path.
ID Predecessor Duration Resources
A None week Persons
B A weeks Persons
C A week Person
D A weeks Persons
E BCD weeks Persons
Select one:
A
ABE
B
ACE
C
ADE
D
ABCE