Question: Draw an Activity - on - Node Diagram, identify project duration and project critical path for the following: Activity name Predecessor ( s ) Duration

Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:
Activity name Predecessor(s) Duration(week)
A None 20
B none 10
C A 10
D A,B 40
E D 10
F E 20
Draw an Activity-on-Arrow Diagram, identify project duration, slack for each activity, and project critical path for the following:
Activity name Predecessor(s) Duration(week)
A none 20
B none 10
C none 10
D A,B 40
E C 10
F C,D 20
G E,F 10
Draw an Activity-on-Node Diagram, identify activity duration, slack for each activity,project duration, and project critical path for the following:
Activity name Predecessor(s) a m b
A none 205090
B none 103040
C none 102030
D A 201030
E B,C 102030
F C,D 203060
G F 10,2050

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!