Question: Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10

  1. Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:

Activity Name

Predecessor(s)

Duration (Weeks)

A

None

20

B

None

10

C

A

10

D

A,B

40

E

D

10

F

E

20