Question: Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following: Activity Name Predecessor(s) Duration (Weeks) A None 20 B None 10
- Draw an Activity-on-Node Diagram, identify project duration and project critical path for the following:
| Activity Name | Predecessor(s) | Duration (Weeks) |
| A | None | 20 |
| B | None | 10 |
| C | A | 10 |
| D | A,B | 40 |
| E | D | 10 |
| F | E | 20 |