Question: Draw an activity on node network diagram and perform forward and backward pass calculations. table [ [ Activity , Predecessor,Duration ] , [ A

Draw an activity on node network diagram and perform forward and backward pass calculations.
\table[[Activity,Predecessor,Duration],[A,-,2],[B,A,5],[C,A,9],[D,A,3],[E,B,6],[F,B, C,4],[G,C, D,2],[H,E, F,4],[I,G, H,2]]
Considering the following table, add lag durations to the AON created in Question 2. Then, perform forward and backward pass calculations.
\table[[Activity,Predecessor,Duration,Lag],[A,-,2,],[B,A,5,],[C,A,9,],[D,A,3,4],[E,B,6,],[F,B, C,4,3(btw B & F)],[G,C, D,2,],[H,E, F,4,],[I,G, H,2,1(btw I & H)],[,G,,]]
 Draw an activity on node network diagram and perform forward and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!