Question: Draw an AOA network diagram representing the project. Use the technique of forward and backward pass and find the slack and float of each activity.
Draw an AOA network diagram representing the project. Use the technique of forward and backward pass and find the slack and float of each activity. Also find the critical path for this project and what is the shortest possible time needed to complete this project?
Activity Initial Node Final Node Estimated Duration 1 10 B 1 3. 12 1 4. D 2 3 4 3 4 6. G 4 5 4 H 4 5 6. J 12 K 7 8 8. 10 69